On November 5, 2026, OpenAI published a National Community Compact and a Compute Campus Policy Blueprint. The compact says each future campus OpenAI owns and operates gets its own local compact. OpenAI says it will pay the full cost of electricity and serving infrastructure, give financial assurances before major spending, write a water plan for each campus, publish water and electricity use and independent noise studies, and not require public officials to sign an NDA as a condition for discussion or negotiation, with narrow exceptions for legitimate security information and trade secrets. The blueprint asks lawmakers to make large power users cover grid costs and to publish tax-incentive terms. The compact pledges annual public reports and independent noise studies but does not specify an independent verification or remedy process for missed commitments; the blueprint proposes reporting and clawback terms for future tax-incentive agreements, not enacted law; the job and user figures are the company's own.

On November 5, 2026, OpenAI's Global Affairs team published two documents about the computing campuses it builds: a National Community Compact and a Compute Campus Policy Blueprint. The compact says what communities can expect from OpenAI at future campuses that OpenAI owns and operates. The blueprint asks federal, state and local policymakers to write rules so that any developer follows similar practices. Both are statements of intent from the company, and the post says they build on commitments announced in January and on specific pledges in Georgia and Ohio.

The compact promises that every future OpenAI-owned and operated campus gets its own local compact, shaped by community input. OpenAI says it will engage residents early enough for their input to change project plans, name a local point of contact for the life of the campus, and report publicly each year on its progress. A common set of commitments follows. On energy, OpenAI says it will pay the full cost of the electricity it uses and of the infrastructure built to serve it, and will give financial assurances before major spending begins, so other customers are protected if a project is delayed, reduced or canceled. On local resources, it will write a water plan for each campus, prioritize closed-loop or low-water cooling, publish site-level water and electricity use, and publish construction plans. It will also commission independent noise studies before operations start and every year after, and publish them. On openness, OpenAI says it will not use non-disclosure agreements with public officials, allowing only narrow protections for legitimate security information, trade secrets, or competitively sensitive information.

On jobs, OpenAI says it will publish the jobs it expects to create, work with unions and training providers, report yearly on hiring and apprenticeships, and invest steadily in priorities that residents choose. The documents give examples. In Effingham County, Georgia, residents helped shape a $4.8 million grant that pays for free school meals for all 14,000 students in the county. In Pike County, Ohio, families named childcare as a priority, which led to a joint $6 million commitment from OpenAI and SB Energy. The compact adds that OpenAI has committed $80 million to community priorities in Effingham County and $40 million in Pike County.

The blueprint is the part aimed at lawmakers. It asks state utility commissions to require large electricity customers to cover the costs they add to the grid and to protect other customers if a project falls through. It asks utilities to ease connection for campuses that can safely cut demand when power is scarce. As an example, OpenAI says its agreement with Georgia Power for the planned Effingham campus lets the utility reduce the power delivered to it by up to 1,000 megawatts during periods of high demand. It asks Congress to speed up transmission upgrades and to restore and expand tax incentives for clean electricity. It calls for public reporting on water, energy, noise and hiring, narrow limits on when developers may ask officials to sign NDAs, and public terms for state and local tax incentives, with measurable commitments and a way to recover benefits if a developer falls short. It also suggests that developers share purchasing plans early so local suppliers can compete, and that employers, building trades unions and community colleges use hiring forecasts to train residents.

The blueprint also contains OpenAI's own claims about the benefits. It says ChatGPT is used by 1.2 billion people each week and that OpenAI served 2.5 million businesses in September 2026. It says the Pike County campus is expected to create 2,500 long-term operating jobs with average annual salaries of $80,000 and 26,000 construction jobs. These are the company's expectations and figures, and we did not check them. The blueprint also argues for export controls on chips and for keeping a US lead in AI over China.

Read the limits of the documents. The compact covers future campuses that OpenAI owns and operates, so sites run by partners are not clearly included. The commitments are voluntary. The compact pledges annual public reports, independent noise studies and financial assurances, but does not specify independent verification or remedies for missed commitments. The blueprint proposes reporting and clawback terms for future tax-incentive agreements; these are not enacted law. Separately, OpenAI says it has signed a Georgia Power supply agreement. OpenAI commits to sustained community investment, while specific projects could vary with local choices; power, water, the NDA condition and reporting are also commitments.

Our reading: this is a public set of promises that residents, reporters and local officials can later measure the company against, and it moves some practices, such as ending NDAs with officials, from private deals into a published standard. It is also a policy lobbying document. Whether it protects households depends on regulators adopting the rules and on OpenAI keeping its reports honest and complete. This is separate from the Grid Protectors program that OpenAI announced on November 2. Ratepayer protection is one of the compact's themes, but the compact and blueprint are the news here. We did not independently verify any figure.

Sources

FAQ

Does the compact apply to every OpenAI data center?

No. It covers future campuses that OpenAI owns and operates, and sites run by partners are not clearly included. The compact pledges annual public reports and independent noise studies. The compact does not specify independent verification or a remedy for missed commitments; the blueprint’s tax-incentive clawback terms are proposals.

What does OpenAI promise about electricity costs?

OpenAI says it will pay the full cost of the electricity it uses and of the infrastructure built to serve it, and give financial assurances before major spending so other customers are protected if a project is delayed or canceled. In Effingham, Georgia, its Georgia Power agreement lets the utility cut supply by up to 1,000 megawatts at peak.

Will OpenAI stop signing NDAs with officials?

For its own future campuses, OpenAI says it will not require public officials to sign an NDA as a condition for discussion or negotiation, allowing only narrow protections for legitimate security information, trade secrets, or competitively sensitive information. The blueprint asks lawmakers to write such limits into rules; it is not yet a legal requirement.